Project three weeks behind

Progetto in ritardo di tre settimane · Project Management · Beginner

The case

You manage a software project with go-live set for November 30. In mid-October the baseline shows a three-week slip on a five-month total duration. The sponsor asks whether you will finish on time. The team is already at full capacity and two features have not started. The budget is nearly fully committed. How do you recover the delay or renegotiate the date without losing the sponsor's trust?

Gestisci un progetto software con go-live fissato al 30 novembre. A metà ottopre la baseline mostra un ritardo di tre settimane su una durata totale di cinque mesi. Lo sponsor chiede se arriverete in tempo. Il team lavora già a pieno ritmo e due funzionalità non sono ancora iniziate. Il budget è quasi tutto impegnato. Come recuperi il ritardo o rinegozi la scadenza senza perdere la fiducia dello sponsor?

Read the case, write how you would solve it — in free text, no prompt required — and Grace's AI judges whether your solution actually works: solved or not solved, with a 0-100 score and coaching feedback that points at what is still uncovered without revealing the answer. Your first 5 evaluations each day are free.

Try to solve this case →

Frequently asked questions

What is the "Project three weeks behind" problem-solving case on Grace?

It is a beginner-level Project Management case based on a real workplace situation. You read the problem, write how you would solve it in free text, and Grace's AI judges whether your solution actually works — or what is still uncovered.

How much XP is this case worth?

Solving a beginner case earns up to 80 XP on the first successful solution. Failed attempts and repeat solutions earn much less — the reward is for cracking it.

Do I need to pay to try this case?

You get 5 free evaluations every day, shared with training scenarios, no credit card required. Beyond that, evaluations cost 1 credit each.

Is there one correct answer to "Project three weeks behind"?

No. Grace judges the substance of your reasoning, not similarity to a script. Different approaches pass, as long as they genuinely solve the problem within the constraints described in the case.

More Project Management cases

All 150 problem-solving cases → · Prompt training scenarios →

From our network

Magellano GPS — Fleet Tracking Made Simple

Real-time GPS tracking, remote engine lock, fuel and CO₂ reporting for your fleet.

Visit magellanogps.com →

From the Agora Intelligence blog

More on agora-intelligence.com →

📱 Download the Android app (beta) iOS coming soon

Say what you mean. Get what you need.

Grace Certified — the AI coach that trains and certifies your prompt engineering — by Agora Intelligence.